Proposed Project:
The aim of the scheme is to reduce traffic circulation in the town centre, improve the environment for pedestrians and cyclists and to enhance the experience for people using the town centre.
Upcoming works: December 3rd to 16th 2018
The proposed design solution requires amendment of the storm water system to accommodate raised pedestrian access and changes to the kerbs and footways.
We'll begin by cleaning the existing drains and pipes to make sure that they're clear and can be CCTV surveyed to check that they are in good working order. We expect that the initial cleaning process will create some noise but we don't expect this to last very long in one area.
For safety, we'll need to close certain roads (though there will still be pedestrian access to residential properties and businesses).
Closures are scheduled for the following nights (10pm-5am):
Mon 3 Dec - Church Road from Osborne Way to Fretherne Road
Tues 4 Dec - Fretherne Road from Church Road to Howardsgate
Wed 5 Dec - Parkway at Howardsgate
Thurs 6 Dec and Fri 7 Dec - Stonehills
Mon 10 Dec to Wed 12 Dec - Howardsgate
Thurs 13 Dec and Fri 14 Dec - Wigmores north
Possible additional closures (6.30pm-5am):
Sun 9 Dec
Sun 16 Dec
Construction:
We expect to start work on the scheme in Spring 2019.
We'll do everything we can to minimise disruption during construction. All businesses will keep access to their premises.
For more information about the project:
Email welwyngardencitytowncentre@hertfordshire.gov.uk.
If you have any concerns about highway issues you can report a fault or phone 0300 123 4047.